cougar creek

Cougar Creek Channel Bank Protection – CAP 1344

Remedial works were conducted to rebuild the Cougar Creek Channel after the devastating 2013 flooding event suffered in Alberta, Canada. Cable Concrete was designed to line the banks and to protect the channel from further erosion in the case of another flood event. Cable Concrete was extensively engineered to the specific design dimensions of the new channel and the hydraulics pertaining to the Cougar Creek watershed.

Product:
Cable Concrete

Location:
Canmore, Alberta

Scope:
CC70 – 49,754 Sqm – 4181 Pieces

Install Date:
01/05/2014

Owner:
The Town of Canmore

Engineer:
ISL Engineering and Land Services Ltd.

Contractor:
Bremner Engineering and Construction Ltd.